name ops-migration-planning
description Structured workflow for infrastructure migration planning including cloud migrations, technology upgrades, and data center transitions.
trigger - Cloud-to-cloud migration - On-premises to cloud migration - Technology platform upgrades - Data center consolidation/exit
skip_when - Application refactoring -> use ring-dev-team specialists - Database schema migrations -> use ring-dev-team specialists - Simple resource moves -> standard change management
related [object Object]

Migration Planning Workflow

This skill defines the structured process for infrastructure migration planning. Use it for systematic, risk-managed migration execution.


Migration Planning Phases

Phase Focus Output
1. Discovery Understand current state Inventory document
2. Assessment Evaluate migration options Assessment report
3. Planning Design migration approach Migration plan
4. Preparation Build target environment Environment ready
5. Migration Execute migration Migrated workloads
6. Validation Verify success Validation report
7. Cutover Switch production traffic Cutover complete
8. Optimization Tune and optimize Optimized state

Phase 1: Discovery

Discovery Checklist

  • Application inventory complete
  • Infrastructure dependencies mapped
  • Data flows documented
  • Integration points identified
  • Current costs documented
  • Performance baselines captured
  • Compliance requirements listed

Discovery Template

## Migration Discovery Report

**Project:** [migration name]
**Date:** YYYY-MM-DD
**Scope:** [on-prem to AWS / AWS to GCP / etc.]

### Application Inventory

| Application | Type | Language | Database | Traffic | Criticality |
|-------------|------|----------|----------|---------|-------------|
| api-service | API | Go | PostgreSQL | 1000 rps | Tier 1 |
| worker | Worker | Python | Redis | N/A | Tier 2 |
| frontend | SPA | React | N/A | 500 rps | Tier 2 |

### Infrastructure Inventory

| Resource | Current | Count | Utilization | Notes |
|----------|---------|-------|-------------|-------|
| Web servers | VM 4CPU/8GB | 10 | 40% avg | Auto-scaled |
| App servers | VM 8CPU/16GB | 20 | 60% avg | Fixed |
| Database | PostgreSQL | 1 primary + 2 replica | 70% | 500GB data |
| Cache | Redis | 3 node cluster | 30% | 10GB data |

### Dependencies

| From | To | Type | Migration Impact |
|------|-----|------|------------------|
| api-service | PostgreSQL | Direct | Must migrate together |
| api-service | Redis | Direct | Can migrate independently |
| frontend | api-service | HTTP | Can migrate independently |

### Data Inventory

| Data Store | Size | Growth Rate | Sensitivity | Retention |
|------------|------|-------------|-------------|-----------|
| PostgreSQL | 500GB | 10GB/month | PII | 7 years |
| S3 | 2TB | 100GB/month | Public | 1 year |
| Redis | 10GB | Stable | Session | N/A |

Phase 2: Assessment

Migration Strategy Options

Strategy Description Best For Risk
Rehost (Lift & Shift) Move as-is Quick migration, legacy Low
Replatform Minor optimizations Cloud-native benefits Medium
Refactor Redesign for cloud Maximum benefit High
Retire Decommission Unused systems None
Retain Keep in place Not suitable for migration None

Assessment Matrix

## Migration Assessment

### Per-Application Strategy

| Application | Strategy | Rationale | Effort | Risk |
|-------------|----------|-----------|--------|------|
| api-service | Replatform | Containerize, use managed DB | Medium | Low |
| worker | Rehost | Already containerized | Low | Low |
| legacy-app | Retire | Unused, no traffic | None | None |

### Migration Waves

| Wave | Applications | Dependencies | Duration | Risk |
|------|--------------|--------------|----------|------|
| 1 | worker, cache | None | 2 weeks | Low |
| 2 | api-service, DB | Worker | 4 weeks | Medium |
| 3 | frontend | API | 1 week | Low |

### Cost Analysis

| Item | Current Monthly | Target Monthly | Delta |
|------|-----------------|----------------|-------|
| Compute | $10,000 | $8,000 | -20% |
| Database | $5,000 | $6,000 | +20% |
| Network | $2,000 | $1,500 | -25% |
| **Total** | **$17,000** | **$15,500** | **-9%** |

### Migration Costs (One-time)

| Item | Cost | Notes |
|------|------|-------|
| Data transfer | $500 | S3 to S3 |
| Parallel running | $8,000 | 2 weeks overlap |
| Consulting | $10,000 | Optional |
| **Total** | **$18,500** | |

Phase 3: Planning

Migration Plan Template

## Migration Plan

**Project:** [name]
**Target Date:** YYYY-MM-DD
**Migration Lead:** [name]

### Timeline

| Phase | Start | End | Duration |
|-------|-------|-----|----------|
| Preparation | YYYY-MM-DD | YYYY-MM-DD | 2 weeks |
| Wave 1 | YYYY-MM-DD | YYYY-MM-DD | 2 weeks |
| Wave 2 | YYYY-MM-DD | YYYY-MM-DD | 4 weeks |
| Wave 3 | YYYY-MM-DD | YYYY-MM-DD | 1 week |
| Optimization | YYYY-MM-DD | YYYY-MM-DD | 2 weeks |

### Resource Requirements

| Role | Allocation | Duration |
|------|------------|----------|
| Migration Lead | 100% | Full project |
| Platform Engineer | 50% | Full project |
| Application Developers | 25% per team | Per wave |
| DBA | 50% | Waves 1-2 |

### Risk Register

| Risk | Likelihood | Impact | Mitigation |
|------|------------|--------|------------|
| Data loss | Low | Critical | Multiple backups, validation |
| Extended downtime | Medium | High | Rollback plan, parallel running |
| Performance degradation | Medium | Medium | Load testing, monitoring |
| Integration failures | Medium | High | Integration testing pre-cutover |

### Rollback Criteria

Migration will be rolled back if ANY of the following occur:
1. Data integrity issues detected
2. Performance degradation >20% vs baseline
3. Critical functionality not working
4. Security vulnerability discovered
5. Stakeholder veto during cutover window

Phase 4: Preparation

Environment Preparation

  • Target infrastructure provisioned
  • Network connectivity established
  • Security controls configured
  • Monitoring set up
  • CI/CD pipelines updated
  • Secrets migrated
  • DNS prepared (low TTL)

Preparation Checklist

## Environment Preparation Status

### Infrastructure

| Component | Status | Verified By | Date |
|-----------|--------|-------------|------|
| VPC/Network | Complete | @platform | YYYY-MM-DD |
| Compute clusters | Complete | @platform | YYYY-MM-DD |
| Database | Complete | @dba | YYYY-MM-DD |
| Cache | Complete | @platform | YYYY-MM-DD |
| Load balancers | Complete | @platform | YYYY-MM-DD |

### Connectivity

| Connection | Source | Target | Status |
|------------|--------|--------|--------|
| VPN tunnel | Source DC | Target VPC | Active |
| Database replication | Source DB | Target DB | Active |
| API connectivity | Source app | Target deps | Verified |

### Data Sync

| Data Store | Method | Lag | Status |
|------------|--------|-----|--------|
| PostgreSQL | Logical replication | <5 sec | Active |
| S3 | Cross-region replication | <15 min | Active |
| Redis | None (rebuild on migration) | N/A | N/A |

Phase 5: Migration Execution

Migration Execution Checklist

## Wave [N] Migration Runbook

**Date:** YYYY-MM-DD
**Start Time:** HH:MM UTC
**Migration Lead:** [name]

### Pre-Migration Checks

- [ ] All team members available
- [ ] Communication channels ready
- [ ] Rollback plan reviewed
- [ ] Stakeholders notified
- [ ] Monitoring dashboards open
- [ ] Data sync lag acceptable

### Migration Steps

| Step | Action | Owner | Expected Duration | Rollback |
|------|--------|-------|-------------------|----------|
| 1 | Freeze source changes | App team | 5 min | Unfreeze |
| 2 | Final data sync | DBA | 15 min | N/A |
| 3 | Stop source application | App team | 2 min | Restart source |
| 4 | Verify data sync complete | DBA | 5 min | N/A |
| 5 | Start target application | App team | 5 min | Stop target |
| 6 | Run smoke tests | QA | 10 min | Stop target |
| 7 | Update DNS/routing | Platform | 5 min | Revert DNS |
| 8 | Monitor for 30 min | All | 30 min | Rollback |

### Post-Migration Verification

- [ ] Application responding
- [ ] Error rates normal
- [ ] Latency within baseline
- [ ] Data integrity verified
- [ ] All integrations working

Phase 6: Validation

Validation Checklist

  • Functional testing passed
  • Performance testing passed
  • Integration testing passed
  • Security validation passed
  • Data integrity verified
  • Monitoring working

Validation Report Template

## Migration Validation Report

**Wave:** [N]
**Date:** YYYY-MM-DD
**Status:** [PASS / FAIL]

### Functional Validation

| Test | Expected | Actual | Status |
|------|----------|--------|--------|
| Login flow | Success | Success | PASS |
| API endpoints | All 200/201 | All 200/201 | PASS |
| Background jobs | Processing | Processing | PASS |

### Performance Validation

| Metric | Baseline | Target | Actual | Status |
|--------|----------|--------|--------|--------|
| p50 latency | 50ms | <60ms | 45ms | PASS |
| p99 latency | 200ms | <250ms | 180ms | PASS |
| Error rate | 0.1% | <0.2% | 0.08% | PASS |
| Throughput | 1000 rps | >900 rps | 1100 rps | PASS |

### Data Validation

| Check | Method | Result |
|-------|--------|--------|
| Row counts | SELECT COUNT(*) | Match |
| Checksums | MD5 on sample | Match |
| Foreign keys | Constraint check | Valid |
| Indexes | Index verification | Present |

Phase 7: Cutover

Cutover Criteria

ALL must be true to proceed with production cutover:

  1. All validation tests passed
  2. Rollback plan tested and ready
  3. Stakeholder approval obtained
  4. Communication sent
  5. On-call team ready
  6. Monitoring in place

Cutover Runbook

## Production Cutover Runbook

**Date:** YYYY-MM-DD
**Cutover Window:** HH:MM - HH:MM UTC
**Cutover Lead:** [name]

### Go/No-Go Checklist

- [ ] Validation report approved
- [ ] Rollback tested within 24h
- [ ] Stakeholder sign-off received
- [ ] Customer communication sent
- [ ] Team availability confirmed
- [ ] War room established

### Cutover Steps

1. **T-30min:** Final go/no-go meeting
2. **T-15min:** Final data sync verification
3. **T-0:** Begin cutover (follow wave runbook)
4. **T+30min:** Initial validation complete
5. **T+2h:** Extended monitoring
6. **T+24h:** Declare migration complete (or rollback)

### Rollback Decision Points

| Time | Trigger | Decision |
|------|---------|----------|
| T+15min | Critical errors | Immediate rollback |
| T+30min | >5% error rate | Rollback recommended |
| T+1h | Performance issues | Evaluate, possible rollback |
| T+2h | Stability issues | Extended evaluation |

Phase 8: Optimization

Post-Migration Optimization

  • Right-size resources based on actual usage
  • Enable cost optimization features
  • Clean up source environment
  • Update documentation
  • Conduct lessons learned
  • Archive migration artifacts

Optimization Template

## Post-Migration Optimization Report

**Migration:** [name]
**Optimization Period:** YYYY-MM-DD to YYYY-MM-DD

### Resource Optimization

| Resource | Initial Size | Optimized Size | Savings |
|----------|--------------|----------------|---------|
| Compute | 10 x m5.xlarge | 8 x m5.large | $400/mo |
| Database | db.r5.2xlarge | db.r5.xlarge | $200/mo |

### Source Environment Cleanup

| Resource | Action | Date | Savings |
|----------|--------|------|---------|
| Old VMs | Terminated | YYYY-MM-DD | $5,000/mo |
| Old storage | Deleted | YYYY-MM-DD | $500/mo |

### Lessons Learned

1. **What went well:** [items]
2. **What could improve:** [items]
3. **Action items for future migrations:** [items]

Anti-Rationalization Table

Rationalization Why It's WRONG Required Action
"Big bang is faster" Big bang has higher risk Migrate in waves
"Skip parallel running" No safety net Run parallel minimum 1 week
"Data validation is overkill" Data loss is catastrophic Validate every migration
"Rollback won't be needed" Optimism != planning Test rollback before cutover
"We can optimize later" Later = never Right-size during optimization phase

Pressure Resistance

User Says Your Response
"Migrate everything this weekend" "Big bang migrations carry unacceptable risk. Wave-based migration is required."
"Skip parallel running, too expensive" "Parallel running is safety net. Cost is justified by risk reduction."
"Data validation takes too long" "Data integrity is non-negotiable. Validation is required before cutover."
"We trust the process, skip rollback test" "Rollback test is mandatory. Untested rollbacks fail when needed."

Dispatch Specialists

For migration planning tasks, dispatch:

Task tool:
  subagent_type: "infrastructure-architect"
  model: "opus"
  prompt: |
    MIGRATION PLANNING REQUEST
    Type: [cloud-to-cloud / on-prem-to-cloud / upgrade]
    Source: [current environment]
    Target: [target environment]
    Scope: [applications/services]
    Timeline: [desired completion]
    Constraints: [budget, compliance, etc.]

For platform preparation:

Task tool:
  subagent_type: "platform-engineer"
  model: "opus"
  prompt: |
    MIGRATION ENVIRONMENT PREPARATION
    Target Platform: [platform details]
    Services: [services to migrate]
    Requirements: [infrastructure requirements]