pre-dev-task-breakdown

@LerianStudio/ring
0
0

Use when decomposing features into implementation units, after Dependency Map Gate 6 passes, when tempted to create giant tasks, or when tasks don't deliver user value

Install Skill

1Download skill
2Enable skills in Claude

Open claude.ai/settings/capabilities and find the "Skills" section

3Upload to Claude

Click "Upload skill" and select the downloaded ZIP file

Note: Please verify skill by going through its instructions before using it.

SKILL.md

name pre-dev-task-breakdown
description Use when decomposing features into implementation units, after Dependency Map Gate 6 passes, when tempted to create giant tasks, or when tasks don't deliver user value

Task Breakdown - Value-Driven Decomposition

Foundational Principle

Every task must deliver working software that provides measurable user value.

Creating technical-only or oversized tasks creates:

  • Work that doesn't ship until "everything is done"
  • Teams working on pieces that don't integrate
  • No early validation of value or technical approach
  • Waterfall development disguised as iterative process

Tasks answer: What working increment will be delivered? Tasks never answer: How to implement that increment (that's Subtasks).

When to Use This Skill

Use this skill when:

  • Dependency Map has passed Gate 6 validation
  • Data Model has passed Gate 5 validation
  • API Design has passed Gate 4 validation
  • About to break down work for sprints/iterations
  • Tempted to create "Setup Infrastructure" as a task
  • Asked to estimate or plan implementation work
  • Before creating subtasks

Mandatory Workflow

Phase 1: Task Identification (Inputs Required)

  1. Approved Dependency Map (Gate 6 passed) - tech stack locked
  2. Approved Data Model (Gate 5 passed) - data structures defined
  3. Approved API Design (Gate 4 passed) - contracts specified
  4. Approved TRD (Gate 3 passed) - architecture patterns documented
  5. Approved Feature Map (Gate 2 passed) - feature relationships mapped
  6. Approved PRD (Gate 1 passed) - business requirements and priorities
  7. Identify value streams - what delivers user value first?

Phase 2: Decomposition

For each TRD component or PRD feature:

  1. Define deliverable - what working software ships?
  2. Set success criteria - how do we know it's done?
  3. Map dependencies - what must exist first?
  4. Estimate effort - T-shirt size (S/M/L/XL, max is XL = 2 weeks)
  5. Plan testing - how will we verify it works?
  6. Identify risks - what could go wrong?

Phase 3: Gate 7 Validation

MANDATORY CHECKPOINT - Must pass before proceeding to Subtasks:

  • All TRD components covered by tasks
  • Every task delivers working software
  • Each task has measurable success criteria
  • Dependencies are correctly mapped
  • No task exceeds 2 weeks effort (XL max)
  • Testing strategy defined for each task
  • Risks identified with mitigations
  • Delivery sequence optimizes value

Explicit Rules

✅ DO Include in Tasks

  • Task ID, title, type (Foundation/Feature/Integration/Polish)
  • Deliverable: What working software ships?
  • User value: What can users do after this?
  • Technical value: What does this enable?
  • Success criteria (testable, measurable)
  • Dependencies (blocks/requires/optional)
  • Effort estimate (S/M/L/XL with points)
  • Testing strategy (unit/integration/e2e)
  • Risk identification with mitigations
  • Definition of Done checklist

❌ NEVER Include in Tasks

  • Implementation details (file paths, code examples)
  • Step-by-step instructions (those go in subtasks)
  • Technical-only tasks with no user value
  • Tasks exceeding 2 weeks effort (break them down)
  • Vague success criteria ("improve performance")
  • Missing dependency information
  • Undefined testing approach

Task Sizing Rules

  1. Small (S): 1-3 points, 1-3 days, single component
  2. Medium (M): 5-8 points, 3-5 days, few dependencies
  3. Large (L): 13 points, 1-2 weeks, multiple components
  4. XL (over 2 weeks): BREAK IT DOWN - too large to be atomic

Value Delivery Rules

  1. Foundation tasks enable other work (database setup, core services)
  2. Feature tasks deliver user-facing capabilities
  3. Integration tasks connect to external systems
  4. Polish tasks optimize or enhance (nice-to-have)

Rationalization Table

Excuse Reality
"This 3-week task is fine" Tasks >2 weeks hide complexity. Break it down.
"Setup tasks don't need value" Setup enables value. Define what it enables.
"Success criteria are obvious" Obvious to you ≠ testable. Document explicitly.
"Dependencies will be clear later" Later is too late. Map them now.
"We don't need detailed estimates" Without estimates, no planning possible. Size them.
"Technical tasks can skip user value" Even infrastructure enables users. Define the connection.
"Testing strategy can be decided during" Testing affects design. Plan it upfront.
"Risks aren't relevant at task level" Risks compound across tasks. Identify them early.
"DoD is the same for all tasks" Different tasks need different criteria. Specify.
"We can combine multiple features" Combining hides value delivery. Keep tasks focused.

Red Flags - STOP

If you catch yourself writing any of these in a task, STOP:

  • Task estimates over 2 weeks
  • Tasks named "Setup X" without defining what X enables
  • Success criteria like "works" or "complete" (not measurable)
  • No dependencies listed (every task depends on something)
  • No testing strategy (how will you verify?)
  • "Technical debt" as a task type (debt reduction must deliver value)
  • Vague deliverables ("improve", "optimize", "refactor")
  • Missing Definition of Done

When you catch yourself: Refine the task until it's concrete, valuable, and testable.

Gate 7 Validation Checklist

Before proceeding to Subtasks, verify:

Task Completeness:

  • All TRD components have tasks covering them
  • All PRD features have tasks delivering them
  • Each task is appropriately sized (no XL+)
  • Task boundaries are clear and logical

Delivery Value:

  • Every task delivers working software
  • User value is explicit (even for foundation)
  • Technical value is clear (what it enables)
  • Sequence optimizes value delivery

Technical Clarity:

  • Success criteria are measurable and testable
  • Dependencies are correctly mapped (blocks/requires)
  • Testing approach is defined (unit/integration/e2e)
  • Definition of Done is comprehensive

Team Readiness:

  • Skills required match team capabilities
  • Effort estimates are realistic (validated by similar past work)
  • Capacity is available or planned
  • Handoffs are minimized

Risk Management:

  • Risks identified for each task
  • Mitigations are defined
  • High-risk tasks scheduled early
  • Fallback plans exist

Gate Result:

  • PASS: All checkboxes checked → Proceed to Subtasks (pre-dev-subtask-creation)
  • ⚠️ CONDITIONAL: Refine oversized/vague tasks → Re-validate
  • FAIL: Too many issues → Re-decompose

Common Violations and Fixes

Violation 1: Technical-Only Tasks

Wrong:

## T-001: Setup PostgreSQL Database
- Install PostgreSQL 16
- Configure connection pooling
- Create initial schema

Correct:

## T-001: User Data Persistence Foundation

### Deliverable
Working database layer that persists user accounts and supports authentication queries with <100ms latency.

### User Value
Enables user registration and login (T-002, T-003 depend on this).

### Technical Value
- Foundation for all data persistence
- Multi-tenant isolation strategy implemented
- Performance baseline established

### Success Criteria
- [ ] Users table created with multi-tenant schema
- [ ] Connection pooling configured (min 5, max 50 connections)
- [ ] Query performance <100ms for auth queries (verified with test data)
- [ ] Migrations framework operational
- [ ] Rollback procedures tested

### Dependencies
- **Blocks**: T-002 (Registration), T-003 (Login), T-004 (Permissions)
- **Requires**: Infrastructure (networking, compute)
- **Optional**: None

### Effort: Medium (M) - 5 points, 3-5 days
### Testing: Integration tests for queries, performance benchmarks

Violation 2: Oversized Tasks

Wrong:

## T-005: Complete User Management System
- Registration, login, logout
- Profile management
- Password reset
- Email verification
- Two-factor authentication
- Session management
- Permissions system

Estimate: 6 weeks

Correct (broken into multiple tasks):

## T-005: Basic Authentication (Register + Login)
- Deliverable: Users can create accounts and log in with JWT tokens
- User Value: Access to personalized features
- Effort: Large (L) - 13 points, 1-2 weeks
- Dependencies: Requires T-001 (Database)

## T-006: Password Management (Reset + Email)
- Deliverable: Users can reset forgotten passwords via email
- User Value: Account recovery without support tickets
- Effort: Medium (M) - 8 points, 3-5 days
- Dependencies: Requires T-005, Email service configured

## T-007: Two-Factor Authentication
- Deliverable: Users can enable 2FA with TOTP
- User Value: Enhanced account security
- Effort: Medium (M) - 8 points, 3-5 days
- Dependencies: Requires T-005

## T-008: Permissions System
- Deliverable: Role-based access control operational
- User Value: Admin can assign roles, users have appropriate access
- Effort: Large (L) - 13 points, 1-2 weeks
- Dependencies: Requires T-005

Violation 3: Vague Success Criteria

Wrong:

Success Criteria:
- [ ] Feature works
- [ ] Tests pass
- [ ] Code reviewed

Correct:

Success Criteria:
Functional:
- [ ] Users can upload files up to 100MB
- [ ] Supported formats: JPEG, PNG, PDF, DOCX
- [ ] Files stored with unique IDs, retrievable via API
- [ ] Upload progress shown to user

Technical:
- [ ] API response time <2s for uploads <10MB
- [ ] Files encrypted at rest with KMS
- [ ] Virus scanning completes before storage

Operational:
- [ ] Monitoring: Upload success rate >99.5%
- [ ] Logging: All upload attempts logged with user_id
- [ ] Alerts: Notify if success rate drops below 95%

Quality:
- [ ] Unit tests: 90%+ coverage for upload logic
- [ ] Integration tests: End-to-end upload scenarios
- [ ] Security: OWASP file upload best practices followed

Task Template

Use this template for every task:

## T-[XXX]: [Task Title - What It Delivers]

### Deliverable
[One sentence: What working software ships?]

### Scope
**Includes**:
- [Specific capability 1]
- [Specific capability 2]
- [Specific capability 3]

**Excludes** (future tasks):
- [Out of scope item 1] (T-YYY)
- [Out of scope item 2] (T-ZZZ)

### Success Criteria
- [ ] [Testable criterion 1]
- [ ] [Testable criterion 2]
- [ ] [Testable criterion 3]

### User Value
[What can users do after this that they couldn't before?]

### Technical Value
[What does this enable? What other tasks does this unblock?]

### Technical Components
From TRD:
- [Component 1]
- [Component 2]

From Dependencies:
- [Package/service 1]
- [Package/service 2]

### Dependencies
- **Blocks**: [Tasks that need this] (T-AAA, T-BBB)
- **Requires**: [Tasks that must complete first] (T-CCC)
- **Optional**: [Nice-to-haves] (T-DDD)

### Effort Estimate
- **Size**: [S/M/L/XL]
- **Points**: [1-3 / 5-8 / 13 / 21]
- **Duration**: [1-3 days / 3-5 days / 1-2 weeks]
- **Team**: [Backend / Frontend / Full-stack / etc.]

### Risks
**Risk 1: [Description]**
- Impact: [High/Medium/Low]
- Probability: [High/Medium/Low]
- Mitigation: [How we'll address it]
- Fallback: [Plan B if mitigation fails]

### Testing Strategy
- **Unit Tests**: [What logic to test]
- **Integration Tests**: [What APIs/components to test together]
- **E2E Tests**: [What user flows to test]
- **Performance Tests**: [What to benchmark]
- **Security Tests**: [What threats to validate against]

### Definition of Done
- [ ] Code complete and peer reviewed
- [ ] All tests passing (unit + integration + e2e)
- [ ] Documentation updated (API docs, README, etc.)
- [ ] Security scan clean (no high/critical issues)
- [ ] Performance targets met (benchmarks run)
- [ ] Deployed to staging environment
- [ ] Product owner acceptance received
- [ ] Monitoring/logging configured

Delivery Sequencing

Optimize task order for value:

Sprint 1 - Foundation:
  Goal: Enable core workflows
  Tasks:
    - T-001: Database foundation (blocks all)
    - T-002: Auth foundation (start, high value)

Sprint 2 - Core Features:
  Goal: Ship minimum viable feature
  Tasks:
    - T-002: Auth foundation (complete)
    - T-005: User dashboard (depends on T-002)
    - T-010: Basic API endpoints (high value)

Sprint 3 - Enhancements:
  Goal: Polish and extend
  Tasks:
    - T-006: Password reset (medium value)
    - T-011: Advanced search (nice-to-have)
    - T-015: Performance optimization (polish)

Critical Path: T-001 → T-002 → T-005 → T-010
Parallel Work: After T-001, T-003 and T-004 can run parallel to T-002

Anti-Patterns to Avoid

Technical Debt Tasks: "Refactor authentication" (no user value) ❌ Giant Tasks: 3+ week efforts (break them down) ❌ Vague Tasks: "Improve performance" (not measurable) ❌ Sequential Bottlenecks: Everything depends on one task ❌ Missing Value: Tasks that don't ship working software

Good Task Names:

  • "Users can register and log in with email" (clear value)
  • "API responds in <500ms for 95th percentile" (measurable)
  • "Admin dashboard shows real-time metrics" (working software)

Confidence Scoring

Use this to adjust your interaction with the user:

Confidence Factors:
  Task Decomposition: [0-30]
    - All tasks appropriately sized: 30
    - Most tasks well-scoped: 20
    - Tasks too large or vague: 10

  Value Clarity: [0-25]
    - Every task delivers working software: 25
    - Most tasks have clear value: 15
    - Value connections unclear: 5

  Dependency Mapping: [0-25]
    - All dependencies documented: 25
    - Most dependencies clear: 15
    - Dependencies ambiguous: 5

  Estimation Quality: [0-20]
    - Estimates based on past work: 20
    - Reasonable educated guesses: 12
    - Wild speculation: 5

Total: [0-100]

Action:
  80+: Generate complete task breakdown autonomously
  50-79: Present sizing options and sequences
  <50: Ask about team velocity and complexity

Output Location

Always output to: docs/pre-development/tasks/tasks-[feature-name].md

After Task Breakdown Approval

  1. ✅ Tasks become sprint backlog
  2. 🎯 Use tasks as input for atomic subtasks (next phase: pre-dev-subtask-creation)
  3. 📊 Track progress per task (not per subtask)
  4. 🚫 No implementation yet - that's in subtasks

Quality Self-Check

Before declaring task breakdown complete, verify:

  • Every task delivers working software (not just "progress")
  • All tasks have measurable success criteria
  • Dependencies are mapped (blocks/requires/optional)
  • Effort estimates are realistic (S/M/L/XL, no >2 weeks)
  • Testing strategy defined for each task
  • Risks identified with mitigations
  • Definition of Done is comprehensive for each
  • Delivery sequence optimizes value (high-value tasks early)
  • No technical-only tasks without user connection
  • Gate 7 validation checklist 100% complete

The Bottom Line

If you created tasks that don't deliver working software, rewrite them.

Tasks are not technical activities. Tasks are working increments.

"Setup database" is not a task. "User data persists correctly" is a task. "Implement OAuth" is not a task. "Users can log in with Google" is a task. "Write tests" is not a task. Tests are part of Definition of Done for other tasks.

Every task must answer: "What working software can I demo to users?"

If you can't demo it, it's not a task. It's subtask implementation detail.

Deliver value. Ship working software. Make tasks demoable.