Dependency Tracking
Overview
Dependency tracking ensures visibility of task relationships, identifies blocking issues early, and enables better resource planning and risk mitigation.
When to Use
- Multi-team projects and programs
- Complex technical integrations
- Cross-organizational initiatives
- Identifying critical path items
- Resource allocation planning
- Preventing schedule delays
- Onboarding new team members
Instructions
1. Dependency Mapping
# Dependency mapping and tracking
class DependencyTracker:
DEPENDENCY_TYPES = {
'Finish-to-Start': 'Task B cannot start until Task A is complete',
'Start-to-Start': 'Task B cannot start until Task A starts',
'Finish-to-Finish': 'Task B cannot finish until Task A is complete',
'Start-to-Finish': 'Task B cannot finish until Task A starts'
}
def __init__(self):
self.tasks = []
self.dependencies = []
self.critical_path = []
def create_dependency_map(self, tasks):
"""Create visual dependency network"""
dependency_graph = {
'nodes': [],
'edges': [],
'critical_items': []
}
for task in tasks:
dependency_graph['nodes'].append({
'id': task.id,
'name': task.name,
'duration': task.duration,
'owner': task.owner,
'status': task.status
})
for blocker in task.blocked_by:
dependency_graph['edges'].append({
'from': blocker,
'to': task.id,
'type': 'Finish-to-Start',
'lag': 0 # days between tasks
})
return dependency_graph
def analyze_critical_path(self, tasks):
"""Identify longest chain of dependent tasks"""
paths = self.find_all_paths(tasks)
critical_path = max(paths, key=len)
return {
'critical_items': critical_path,
'total_duration': sum(t.duration for t in critical_path),
'slack_available': 0,
'any_delay_impacts_schedule': True,
'monitoring_frequency': 'Daily'
}
def identify_blocking_dependencies(self, tasks):
"""Find tasks that block other work"""
blocking_tasks = {}
for task in tasks:
blocked_count = sum(1 for t in tasks if task.id in t.blocked_by)
if blocked_count > 0:
blocking_tasks[task.id] = {
'task': task.name,
'blocking_count': blocked_count,
'blocked_tasks': [t.id for t in tasks if task.id in t.blocked_by],
'status': task.status,
'due_date': task.due_date,
'risk_level': 'High' if blocked_count > 3 else 'Medium'
}
return blocking_tasks
def find_circular_dependencies(self, tasks):
"""Detect circular dependency chains"""
cycles = []
for task in tasks:
visited = set()
if self.has_cycle(task, visited, tasks):
cycles.append({
'cycle': visited,
'severity': 'Critical',
'action': 'Resolve immediately'
})
return cycles
def has_cycle(self, task, visited, tasks):
visited.add(task.id)
for blocker_id in task.blocked_by:
blocker = next(t for t in tasks if t.id == blocker_id)
if blocker.id in visited:
return True
if self.has_cycle(blocker, visited, tasks):
return True
visited.remove(task.id)
return False
2. Dependency Management Board
Dependency Tracking Dashboard:
Project: Platform Migration Q1 2025
---
Critical Path (Blocking Progress):
Task: Database Migration
ID: TASK-101
Owner: Data Team
Duration: 20 days
Status: In Progress (50%)
Due Date: Feb 28, 2025
Blocked By: Schema validation (TASK-95) - DUE TODAY
Blocks: 6 downstream tasks
Risk Level: HIGH
Action Items:
- Daily standup with Data Team
- Schema validation must complete by EOD
- Have rollback plan ready
---
Task: API Contract Finalization
ID: TASK-102
Owner: Backend Team
Duration: 10 days
Status: Pending (Blocked)
Depends On: Database Migration (TASK-101)
Blocks: Frontend implementation (TASK-103), Testing (TASK-104)
Slack Time: 0 days (critical)
Early Start: Mar 1, 2025
Action Items:
- Start draft specifications now
- Review with Frontend team
- Have alternative approach ready
---
High-Risk Dependencies:
Dependency: Third-party Integration
From: Payment Service API (vendor)
To: Checkout System (TASK-150)
Type: External/Uncontrollable
Status: At Risk (Vendor delay reported)
Mitigation: Mock service implementation, alternative vendor identified
Escalation Owner: Product Manager
---
By Team Dependencies:
Backend Team:
- Database migration → API development
- Schema design → Data layer implementation
External: Awaiting Payment Gateway API docs
Frontend Team:
- API contracts → UI implementation
- Design system → Component development
Dependency on Backend: API contract specs (scheduled Feb 20)
DevOps Team:
- Infrastructure provisioning → Testing environment
- Kubernetes setup → Staging deployment
External: Cloud provider quota approval
3. Dependency Resolution
// Handling and resolving dependency issues
class DependencyResolution {
resolveDependencyConflict(blocker, blocked) {
return {
conflict: {
blocking_task: blocker.name,
blocked_task: blocked.name,
reason: 'Circular dependency detected'
},
resolution_options: [
{
option: 'Parallelize Work',
description: 'Identify independent portions that can proceed',
effort: 'Medium',
timeline: 'Can save 5 days'
},
{
option: 'Remove/Defer Blocker',
description: 'Defer non-critical requirements',
effort: 'Low',
timeline: 'Immediate'
},
{
option: 'Create Interim Deliverable',
description: 'Deliver partial results to unblock downstream',
effort: 'High',
timeline: 'Can save 8 days'
}
]
};
}
breakDependency(dependency) {
return {
current_state: dependency,
break_strategies: [
{
strategy: 'Remove unnecessary dependency',
action: 'Refactor to eliminate requirement',
risk: 'Low if verified'
},
{
strategy: 'Mock/Stub external dependency',
action: 'Create temporary implementation',
risk: 'Medium - ensures compatibility'
},
{
strategy: 'Parallel development',
action: 'Make assumptions, validate later',
risk: 'Medium - rework possible'
},
{
strategy: 'Resource addition',
action: 'Parallelize work streams',
risk: 'Low but costly'
}
]
};
}
handleBlockedTask(task) {
return {
task_id: task.id,
status: 'Blocked',
blocker: task.blocked_by[0],
time_blocked: task.calculateBlockedDuration(),
actions: [
'Notify team of blockage',
'Escalate if critical path',
'Identify alternative work',
'Schedule resolution meeting',
'Track blocker closure date'
],
escalation: {
immediate: task.is_critical_path,
owner: task.program_manager,
frequency: 'Daily standup until resolved'
}
};
}
}
4. Dependency Dashboard Metrics
Key Metrics:
Critical Path Health:
- Items on Critical Path: 12
- At-Risk Items: 2 (17%)
- Completed: 4 (33%)
- On Track: 6 (50%)
- Behind: 2 (17%)
Dependency Status:
- Total Dependencies: 28
- Resolved: 18
- Active: 8
- At Risk: 2
- Circular: 0 (Good!)
Blocking Impact:
- Tasks Currently Blocked: 3
- Team Members Idle: 2
- Blocked Effort (person-hours): 24
- Estimated Cost of Blockage: $2,400
Escalations:
- Open: 1 (Database migration dependency)
- Resolved This Week: 0
- Average Resolution Time: 2.3 days
Best Practices
✅ DO
- Map dependencies early in planning
- Update dependency tracking weekly
- Identify and monitor critical path items
- Proactively communicate blockers
- Have contingency plans for key dependencies
- Break complex dependencies into smaller pieces
- Track external dependencies separately
- Escalate blocked critical path items immediately
- Remove unnecessary dependencies
- Build in buffer time for risky dependencies
❌ DON'T
- Ignore external dependencies
- Leave circular dependencies unresolved
- Assume dependencies will "work out"
- Skip daily monitoring of critical path
- Communicate issues only in status meetings
- Create too many dependencies (couples systems)
- Forget to document dependency rationale
- Avoid escalating blocked critical work
- Plan at 100% utilization (no buffer for dependencies)
- Treat all dependencies as equal priority
Dependency Management Tips
- Color-code by risk level in tracking tools
- Weekly review of blocked/at-risk items
- Maintain updated dependency diagram
- Escalate after 1 day of blockage on critical path
- Build 15-20% buffer for risky dependencies