Florida environmental permitting expertise. Invoke for SJRWMD permits, wetland assessments, flood zone analysis, or stormwater requirements.

Install Skill

1Download skill
2Enable skills in Claude

Open claude.ai/settings/capabilities and find the "Skills" section

3Upload to Claude

Click "Upload skill" and select the downloaded ZIP file

Note: Please verify skill by going through its instructions before using it.

SKILL.md

name environmental-permitting
description Florida environmental permitting expertise. Invoke for SJRWMD permits, wetland assessments, flood zone analysis, or stormwater requirements.
allowed-tools Read, Write, Bash

Florida Environmental Permitting Skill

When to Invoke

  • Questions about SJRWMD permits
  • Wetland assessment needs
  • Flood zone determination
  • Stormwater management
  • Environmental constraints

SJRWMD Permit Types

ERP (Environmental Resource Permit)

Required for:

  • Projects disturbing >1 acre
  • Work in wetlands
  • Stormwater systems
  • Activities in/near surface waters

Thresholds:

  • <4,000 sq ft impervious: Exempt
  • 4,000 sq ft - 1 acre: Noticed General
  • 1 acre: Individual permit

WUP (Water Use Permit)

Required for:

  • Irrigation systems >1 acre
  • Commercial water use
  • Dewatering operations

Flood Zone Determination

FEMA Zone Designations

Zone Risk Level Requirements
X Minimal Standard construction
A High (no BFE) Elevation required
AE High (BFE known) Build above BFE
VE Coastal high hazard Strict requirements

Building Requirements by Zone

  • Zone X: No special requirements
  • Zone A/AE: Lowest floor ≥ BFE + 1 ft
  • Zone VE: Open foundation, ≥ BFE + 1 ft

Wetland Assessment Process

  1. Desktop Review

    • Check National Wetlands Inventory (NWI)
    • Review aerial imagery
    • Identify potential wetland areas
  2. Field Delineation (if needed)

    • Hire certified wetland delineator
    • Flag wetland boundaries
    • Prepare delineation report
  3. Permit Strategy

    • Avoid: Best option
    • Minimize: Reduce impact
    • Mitigate: Compensate for unavoidable impact

Stormwater Requirements

Retention/Detention

  • Pre vs post development runoff
  • 25-year, 24-hour storm
  • Water quality treatment

Common Solutions

  • Retention ponds
  • Dry detention
  • Swales
  • Underground systems

Timeline Estimates

Permit Review Time
ERP General 30 days
ERP Individual 90 days
WUP 90 days
Wetland Delineation 30-60 days

Key Contacts

  • SJRWMD: 386-329-4500
  • FDEP: 850-245-2118
  • US Army Corps: 904-232-1666