Project Schedule Template Expert
Expert in project scheduling, WBS, timeline management, and resource allocation.
Work Breakdown Structure (WBS)
wbs_principles:
100_percent_rule: "WBS must include 100% of project scope"
mutual_exclusivity: "No overlapping work between elements"
appropriate_detail: "Break down until estimable (8-80 hours)"
numbering:
level_1: "1.0, 2.0 (Phases)"
level_2: "1.1, 1.2 (Deliverables)"
level_3: "1.1.1 (Work packages)"
wbs_template:
- id: "1.0"
name: "Initiation"
deliverables:
- "1.1 Project Charter"
- "1.2 Stakeholder Analysis"
- id: "2.0"
name: "Planning"
deliverables:
- "2.1 Project Plan"
- "2.2 Technical Design"
- id: "3.0"
name: "Execution"
deliverables:
- "3.1 Development"
- "3.2 Testing"
- id: "4.0"
name: "Deployment"
deliverables:
- "4.1 Production Release"
- id: "5.0"
name: "Closure"
deliverables:
- "5.1 Documentation"
- "5.2 Lessons Learned"
Dependencies
dependency_types:
finish_to_start:
code: "FS"
description: "Successor starts when predecessor finishes"
most_common: true
start_to_start:
code: "SS"
description: "Both start together"
finish_to_finish:
code: "FF"
description: "Both finish together"
lag_lead:
lag: "FS+5 = Start 5 days after"
lead: "FS-3 = Start 3 days before finish"
Duration Estimation
three_point_estimation:
formula: "(O + 4M + P) / 6"
definitions:
optimistic: "Best case (10% probability)"
most_likely: "Most probable duration"
pessimistic: "Worst case (10% probability)"
example:
optimistic: 10
most_likely: 15
pessimistic: 26
result: "16 days"
risk_buffers:
low_risk: "10-15%"
medium_risk: "20-30%"
high_risk: "40-50%"
Resource Allocation
resource_planning:
max_utilization: "80% recommended"
buffer: "20% for meetings, admin, unexpected"
capacity_formula: "Working Days × Hours/Day × Availability %"
resource_leveling:
techniques:
- "Delay non-critical tasks"
- "Split tasks"
- "Add resources"
- "Overtime (short-term only)"
Critical Path
critical_path:
definition: "Longest path determining minimum duration"
characteristics:
- "Zero total float"
- "Delay impacts project end date"
calculations:
early_start: "Max(predecessor early finishes)"
early_finish: "Early start + Duration"
late_finish: "Min(successor late starts)"
late_start: "Late finish - Duration"
total_float: "Late start - Early start"
Phase Guidelines
phase_duration:
initiation: "5-10%"
planning: "15-25%"
execution: "50-70%"
closure: "5-10%"
Лучшие практики
- WBS first — начинайте с полной декомпозиции работ
- Realistic estimates — используйте трёхточечную оценку
- Buffer planning — закладывайте буферы на риски
- Critical path focus — приоритизируйте критический путь
- Resource leveling — избегайте перегрузки
- Regular updates — обновляйте расписание еженедельно