Plan infrastructure capacity for expected load. Use when sizing systems, planning for growth, or analyzing resource requirements. Covers load estimation and resource sizing.

Install Skill

1Download skill
2Enable skills in Claude

Open claude.ai/settings/capabilities and find the "Skills" section

3Upload to Claude

Click "Upload skill" and select the downloaded ZIP file

Note: Please verify skill by going through its instructions before using it.

SKILL.md

name capacity-planning
description Plan infrastructure capacity for expected load. Use when sizing systems, planning for growth, or analyzing resource requirements. Covers load estimation and resource sizing.
allowed-tools Read, Bash, Glob, Grep

Capacity Planning

Workflows

  • Baseline: Measure current resource usage
  • Forecast: Project future growth
  • Size: Calculate required resources
  • Buffer: Add headroom for spikes
  • Monitor: Track actual vs. predicted

Key Metrics

Compute

  • CPU utilization (target: 60-70%)
  • Memory usage
  • Request latency (P50, P95, P99)

Storage

  • Disk IOPS
  • Throughput (MB/s)
  • Capacity growth rate

Network

  • Bandwidth utilization
  • Connection counts
  • Packet loss

Estimation Framework

Little's Law

L = λ × W

L = Average number of items in system
λ = Average arrival rate
W = Average time in system

Example Calculation

Given:
- 1000 requests/second
- 100ms average response time

Required concurrent connections:
L = 1000 × 0.1 = 100 concurrent connections

Resource Sizing

Database Connections

connections = (requests_per_second × avg_query_time) × 1.5

Memory

memory = (concurrent_users × memory_per_user) + base_overhead

CPU Cores

cores = (peak_rps × cpu_time_per_request) / target_utilization

Growth Planning

Traffic Growth

  • Historical growth rate
  • Planned marketing/launches
  • Seasonal patterns

Data Growth

  • Records per day
  • Record size
  • Retention policy

Capacity Planning Document

  1. Current state metrics
  2. Growth assumptions
  3. Resource projections (3, 6, 12 months)
  4. Cost estimates
  5. Scaling triggers and thresholds